Campus construction news
Get the dirt on campus construction here.
Campus construction update
Construction of the $44.5 million Education Building is proceeding toward on-time completion in November 2013. > Full story.
State Building Commission approves two UW-Eau Claire projects
The State Building Commission approved two University of Wisconsin-Eau Claire projects for inclusion in the 2013-15 state capital budget: a new upper-campus residence hall and Garfield Avenue corridor improvements. > Full story .
Restoration project highlights beauty of Little Niagara Creek
The restoration project removed silt and sediment from the stream bed, restored eroded soil banks that have slumped into the stream, removed invasive plant species, and fortified the new banks with rock and soil with a native seed mixture. > Full story. 
Upcoming activities
- Lawn irrigation system installations
- Old Davies Center site restoration
Target dates
Dates/times approximate and subject to change
May 2013
Green space construction on old Davies site completed
November 2013
Education Building construction completed
Spring 2014
Classes begin in new Education Building