Education Building Committee
New education building
The new education building will house UW-Eau Claire's College of Education and Human Sciences administrative units; classroom space; the departments of education studies, English, foreign languages and special education; and select student support services, including Services for Students with Disabilities, the Student Success Center (providing writing, math and other academic support) and the Office of Multicultural Affairs.
Project budget: $44.5 million
Current status: A groundbreaking ceremony for the new Education Building and a farewell to Campus School were held on
Friday, May 18, 2012. Campus School is being razed to make way for the
new building. Construction began in late May/early June. The Education
Building is expected to be completed in fall 2013.
Approximate building size: 170,000 square feet
Location: Between Schneider Social Science Hall and Brewer Hall/Kjer Theatre/Zorn Arena complex. (Campus School is being razed as a part of this project.)
Anticipated timeline:
- October 2011: Design complete
- May 2012: Begin construction
- November 2013: Construction completed
- Spring 2014: Classes begin in new building